Juergen Faelker
esa villafranca del castillo satellite tracking station (iso/scc),
p.o. box 50727, 28080 madrid/spain,
e-mail: jfaelker@vmprofs.vilspa.esa.es; fax: +34-1-8131139
Inside of the cryostat vessel the telescope, type Ritchey-Chretien, and the four " cold " focal plane units
of the scientific instruments are located underneath of the 60 cm primary mirror. They operate at around
3 K.
The extremely low temperature is achieved by boiling off the liquid
Helium. The instruments were conceived and built by various scientific institutions external to ESA. The four instruments carried on-
board ISO are: The Infrared Camera (CAM), the Long Wavelength Spectrometer (LWS), the Photo-
Polarimeter with imaging capability (PHT) and the Short Wavelength Spectrometer (SWS). The cryostat
cover was jettisoned on 27 November and from this moment onwards, the scientific instruments started
to receive infrared radiation from space. The Helium bath achieved thermal equilibrium at 1.724 K some
three weeks after launch.
The ISO satellite has no on-board data storage. Therefore, to carry out any scientific observations,
continuous real-time contact with a ground station is essential. In the absence of ground station contact, the
satellite has a variety of safe and autonomous modes enabling it to survive up to 72 hours until contact is
re-established.
The LEOP activities were conducted according to the Flight Operations Plan (FOP). Beside a temperature
anomaly on the cooling of the CCD of Star Tracker-1 (STR), which was resolved shortly after, all LEOP
activities were executed as planned. After three days, the first part of the Flight Control Team moved to
the ESA Villafranca Satellite Tracking Station (VILSPA), near Madrid/Spain, where the ISO dedicated
Spacecraft Control Centre (SCC) and the Science Operations Centre (SOC) are co-located. During LEOP,
the SCC and SOC were in the so called "Listen- In" mode, i.e. only telemetry was passed on in parallel to
the OCC. No instrument operations were conducted during LEOP. Handover of operations from the OCC
to the SCC took place as planned on 21 November, i.e. with the beginning of revolution 4, which
concluded LEOP.
The SCP showed that the overall spacecraft status is excellent and that all subsystems performing within
or above specifications. Although the cryo cover was not released yet, the electrical switch-on phase and
check out of the scientific instruments commenced. On 24 November, close to perigee 7, the apogee
lowering manoeuvre was performed and ISO reached its mission orbit, as shown in Figure-2 .
The orbit determination result on 24 November, include the effect of the 39 min. 20.5 sec. Delta-V manoeuvre,
executed at 02:50:04 UT prior to perigee 7. Epoch 24 November at 03:45:29 UT (perigee 7)
.
The major event during this phase was the cryostat cover release on 27 November at 10:27 UT. Verification of the
jettisoning was immediately seen in telemetry by monitoring the gyroscope's outputs. Shortly after, the
temperatures of the cryo subsystem indicated that ISO was indeed viewing cold space.
The cool-down
| Height of perigee | 1004 | Km |
| Height of apogee | 70611.1 | Km |
| Semi-major axis | 42374.6 | Km |
| Eccentricity | 0.825788 | |
| Inclination | 5.1975 | Deg. |
| Ascending node | 308.7 | Deg. |
| Argument of perigee | 115.78 | Deg. |
| True anomaly | 359.98 | Deg. |
of the cryogenics was well in line with the predictions of the thermal model and equilibrium
was reached some three weeks after launch. The
Helium-II bath temperature settled at 1.724 K
(spec: 1.7 to 1.9 K) and the temperature about
the Optical Support Structure (OSS), was
measured around 2.8 K (spec: 2.4 to 3.4 K). All
nominal functional modes of the SVM have been
successfully
verified. After cryo-cover ejection the Quadrant Star Sensor (QSS) was switched on
and calibrated and the first QSS/STR
misalignment calibration performed to measure
the offset between the telescope boresight and
the Star Tracker (STR). A misalignment of 205
arcsec was measured, which was well within
specifications. Since then, the QSS/STR
misalignment calibration is performed once per
revolution to determine variations due to thermo-elastic effects. The misalignment
measured is then applied automatically to correct
the attitude quaternions of the pointing
requests.
The pointing performance of the Attitude and Orbit Control Subsystem (AOCS), as shown in Figure-3, is considerably better than specifications. Similar to the SVM, all nominal modes of the PLM have been
successfully verified. The Helium-II flow rate is well within limits leading to an anticipated lifetime of
24 +/- 2 months, compared with the baseline of 18 months.
Direct Liquid Content Measurements (DLCM) are required to determine the remaining He-II mass and hence, the lifetime.
Figure-3. ISO Pointing Performance
| UNITS | IN-ORBIT | SPEC. | |
| Relative Pointing Error (RPE) , 2 sigma-half cone | arcsec | 0.5 | < 2.7 |
| Absolute Pointing Drift (APD) | arcsec/h | < 0.1 | < 2.8 |
| Absolute Pointing Error (APE) | arcsec | < 4.0 | < 11.7 |
The Focal Plane Geometry Calibration of the four instruments occupied a large part of the Satellite
Commissioning Phase (8 revolutions), because the procedures used to acquire up to 5 stars for the PHT
and the SWS experiments with the Star Tracker using the restricted search and tracking mode, needed to be interleaved manually with an executing Central Command Schedule (CCS), whereby all groups
(SOC/SCC/Instrument Dedicated Teams (IDT)/PROJECT and FLIGHT DYNAMICS) were required to
work very closely together. Figure-4 shows the final offsets determined for each of the instruments and
their relevant apertures.
| INSTRUMENT | UNITS | Y-AXIS | Z-AXIS |
| CAM | arcsec | 2.65 | 7.45 |
| LWS | " | 13.5 | 4.5 |
| PHT-1 | " | -9.5 | -3.9 |
| PHT-2 | " | -9.5 | -3.9 |
| PHT-3 | " | -6.8 | -5.1 |
| SWS-1 | " | 1.5 | -19.6 |
| SWS-2 | " | 4.7 | -22.2 |
| SWS-3 | " | 9.3 | -24.5 |
Data Server system (ODS-1/2). The ODS constitutes the interface between the spacecraft control system
of the SCC and that of the SOC as far as science real-time data reception in form of Telemetry Distribution
Formats (TDF) is concerned. The latter contains as well telecommand history data and specially provided
derived telemetry parameters for instrument monitoring and control purposes required by the Real-Time
Analysis (RTA) and Quick-Look Analysis (QLA) run on the four instrument workstations (one dedicated
per instrument) of the SOC. The ODS as well provides the interface between the Mission Planning Phase-
1 (MMP1) of the SOC and that of the SCC (MPP2).
Furthermore, the ODS provides the short history archive of the science telemetry, which is accessible from
the SOC Science Data Processing system. The NETWORK INTERFACE provides the connectivity of
the IDCS with the ground stations through the Integrated Switching System (ISS), as part of the OPSNET.
Support functions are provided for: Spacecraft Performance Evaluation (SPEVAL) required to determine
all aspects of spacecraft performance which can impact the life of the mission and mission efficiency.
Spacecraft on-board software maintenance for the AOCS, STR and the OBDH. Communications Services
are provided to interface with the Ground Stations, and with ESOC for ranging and orbit-related activities.
Two Spacecraft Hybrid Simulators are provided to support a variety of tasks such as procedure testing and
validation, AOCS on-board software maintenance and validation, and spacecraft anomaly investigation.
All scientific observations must satisfy the spacecraft constraints. Additionally, there are constraints in
the use of the instruments and of the Star Tracker (STR). Due to the highly eccentric orbit with a perigee
of 1000 Km, the satellite passes the outer and inner radiation belts of the earth, requiring the instruments
to be switched on/off once per revolution, while the STR cannot be used +/- 3 hours around perigee. The
instrument constraints are based on satellite altitude and are separated in the electrical use (26.500 Km
leaving perigee to 21.200 Km towards perigee entry). Furthermore, scientific observations can be
performed only within 43.200 Km leaving perigee and 37.250 Km prior to perigee entry, some 17 hours
per revolution (orbit).
Figure-6. ISO Central Command Schedule Overview
|
TIME [relative] |
EVENT | ACTIVITY |
| 00:00:00 | PSF_START | Schedule start time; equals to perigee crossing time. |
| + 00:15:00 | AOS_TM | Acquisition Of Signal - Villafranca Station. (+/- Y Antenna) |
| + 00:15:00 | AOS_CHK_OPEN | S/C status check and re-configuration from perigee passage. |
| + 00:35:00 | AOS_CHK_CLOSE | |
| + 00:40:00 | MOUT | Message OUT: Next on-board antenna (+/- Y) change. |
| + 01:00:00 | PPL_LOAD_OPEN | Pre-planned Pointing List uplink for 72 hours safe pointing; |
| + 01:10:00 | PPL_LOAD_CLOSE | TT-Cmds for PPM entry and Instruments off. |
| + 01:55:00 | ACTIV_OPEN | Activation window - 4 Instruments switch on and activation |
| + 03:20:00 | ACTIV_CLOSE | begins at altitude of 26.500 Km. |
| + 03:20:00 | SOPS_OPEN | Reaction Wheel Biasing for science window to prevent |
| + 03:25:00 | SOPS_CLOSE | autonomous unloading and wheel zero-speed crossing. |
| + 03:25:00 | ACAL_OPEN | Calibration window - Attitude update, transition PPM to |
| + 04:00:00 | ACAL_CLOSE | Fine Pointing Mode (FPM), QSS/STR calibration. |
| + 04:00:00 | OBS_OPEN | Observation window - Scientific observations commence. |
| + 10:18:00 | AOS_TM | Acquisition Of Signal - Goldstone Station. |
| + 12:46:00 | OBS_CLOSE | Mid-Orbit Calibration LWS/PHT/CAM (-17min) continues. |
| + 12:46:00 | HAND_OPEN | Handover window - TM/TC from Villafranca to Goldstone |
| + 12:56:00 | HAND_CLOSE | Mid-Orbit calibration LWS/PHT/CAM (+9 min) continues. |
| + 12:56:00 | SOPS_OPEN | Reaction Wheel Biasing (as above) |
| + 13:01:00 | SOPS_CLOSE | |
| + 13:01:00 | OBS_OPEN | Mid-Orbit calibration LWS/PHT/CAM (+4 min.) continues. |
| + 13:28:00 | LOS_TM | Loss Of Signal - Villafranca Station |
Figure-6. ISO Central Command Schedule Overview (cont'd.)
|
TIME [relative] |
EVENT | ACTIVITY |
| + 20:55:00 | OBS_CLOSE | Observations must stop at altitude 37.200 Km + PPM entry. |
| + 20:56:00 | STR_STOP | At - 3 hours prior perigee crossing time. |
| + 20:56:00 | PPL_LOAD_OPEN | New Pre-planned Pointing List uplink for 72 hours safety. |
| + 21:06:00 | PPL_LOAD_CLOSE | |
| + 21:06:00 | SOPS_OPEN | Reaction Wheel Biasing to avoid autonomous unloading |
| + 21:11:00 | SOPS_CLOSE | during perigee passage - affecting orbit. |
| + 21:11:00 | DEACTIV_OPEN | Deactivation window - 4 instruments deactivation and |
| + 22:16:00 | DEACTIV_CLOSE | switch off for perigee passage. |
| + 22:16:00 | LOS_CHK_OPEN | S/C status check and reconfiguration for perigee passage; |
| + 22:31:00 | LOS_CHK_CLOSE | Instruments switch off (backup) at + 22:27:00 (21.000 Km) |
| + 22:33:00 | MOUT | Switch S-Band antenna (+/- Y) required for next AOS+EOT |
| + 22:46:00 | PPM_ENTRY | Latest possible time for PPM entry. |
| + 23:46:00 | LOS_TM | Loss Of Signal - Goldstone Station. |
| + 23:56:00 | PSF_END | Schedule end time; equals to perigee crossing time. |
Future observatory type missions should adapt the ISO experience as a general guideline, although some areas have been identified, where improvements or changes would result in a more effective and cost efficient approach. The ground driven command schedule is highly susceptible to ground segment problems. This should be an on-board application task. On-board mass memory storage is required to reduce the costs for a second ground station, required to provide nearly 24 hours real-time support. The splitting of responsibilities between instrument operations (SOC) and spacecraft operations (SCC) is inefficient and a cost-driver. Instruments loosing their RAM patches after switch-off and hence, requiring the uplink of the said RAM patches once per revolution, is an inefficient and time consuming approach. The activation and deactivation process should be an on-board application task. The latter introduces a heavy load on the commanding system. The mission planning system (MPP1 and MPP2) requires streamlining. Too many parties are involved in the planning process, which makes the process slow and in some areas inflexible and hence, not efficient, although it works surprisingly well.